Introduction
OpenEVSE Store - Purchase this OpenEVSE Kit
Warning Assembly of a Electric Vehicle charging station requires wiring Alternating Current (AC) components that will be exposed to voltages from 100 to 250v. If you do not have the experience and knowledge required to safely work with AC voltages please consult with an experienced electrician for assistance and inspection of your work.
Note Regularly inspect your charging station. Pay special attention to excess heat, components, handles, and wiring will be warm but they should not be HOT...
Always Disconnect your charging station from power before performing an inspection and/or maintenance
-
-
Mount Display to lid with 4 6mm screws.
-
Option 1 - No button. If your station is open to the public you may wish to configure via WiFi and not install a button.
-
Option 2 - Drill a 16mm hole between the menu icon and the center dimple and install the included mechanical button.
-
Optional Upgrade - Remove film from the double sided tape and mount touch button. Line up square grid area with the menu icon printed on the enclosure.
-
Remove film from the double sided tape and mount WiFi Module.
-
-
-
Mount button with O-ring seal on the outside. Screw on the large hex nut from the inside.
-
Connect harness to the screw terminals of the push button.
-
-
-
Position the plate with the 4 holes for the OpenEVSE controller up top and the Earth Ground bus bar on the right.
-
Mount hex standoffs to the top side of the plate with 6 mm screws.
-
Mount ground bar to the plate with 2 - 5/8" self threading screws.
-
Mount the Struthers-Dunn relay using 2 - 1/2" self threading screws.
-
-
-
Connect both keyed wiring harnesses to OpenEVSE controller.
-
Connect DC Relay 1 GND (Black) to the bottom middle coil terminal. Tighten screw.
-
Connect DC Relay C +12v (Red) to the top middle coil terminal. Tighten screw.
-
Connect AC INPUT 1 to the bottom left power terminal. Start screw, but leave loose additional power wire added later.
-
Connect AC INPUT 2 to the top left power terminal. Start screw, but leave loose additional power wire added later.
-
Connect AC_TEST 1 and 2 to the top and bottom right power terminals. Start screw, but leave loose additional power wire added later.
-
-
-
Connect the red wire on the UBEC WiFi power supply to +12v DC screw terminal on the OpenEVSE controller.
-
Connect the black wire on the UBEC WiFi power supply to the Ground screw terminal on the OpenEVSE controller.
-
Connect the keyed 4 pin GFCI coil to the OpenEVSE controller.
-
Connect the keyed 2 pin Current Measurement coil to the OpenEVSE controller.
-
-
-
-
Insert EV Cable through the Cable Gland on the right and tighten.
-
Thread ALL hot and neutral lines through the 4 wire GFCI coil with the orange self test loop.
-
Thread only ONE hot set line through the Current Measurement Coil.
-
-
-
Connect AC Input 2 to the relay top left power terminal.
-
Connect AC Load 2 to the relay top right power terminal
-
Connect AC Input 1 to the relay bottom left power terminal.
-
Connect AC Load 1 to the relay bottom right power terminal
-
-
-
Connect the AC Input Earth Ground to the Ground block.
-
Connect the EV Output Earth Ground to the Ground block.
-
Connect the EV Output Control Pilot (CP) to PLT on the OpenEVSE Controller.
-
-
-
Connect Display cable (4 wires) and the WiFi Cable (2 wires) to the OpenEVSE Controller.
-
Connect the UBEC power supply to the WiFi harness. Match Red to Red and Black to Black.
-
Connect the WiFi Harness to the WiFi Module.
-
-
-
Using 4 - 6mm screws. Mount display module to the lid.
-
Connect 4 pin connector to display module.
-
Connect the 3 position connector (2 wires attached) to the display module and the ends to the button.
-
Mount WiFi to the left of the button with the header pins to the far left.
-
-
-
When adjusting, be gentle. Do not force past the stop in either direction. If forced past the stop, the part will no longer function.
-
Secure the enclosure lid. Tighten the screws slowly alternating across and top, middle and bottom.
-
-
-
To Enter the Menu Press and hold the button (long press). Press and release (short press) to scroll through Options.
-
Cancel: I did not complete this guide.