Skip to main content

Pending Edits to Current - v6.5.1 OpenEVSE Advanced

Note: Accepting or denying any edit implicitly applies to all earlier pending edits to the same step or introduction.

Step #7 edited: [Step edited]

Edited by Tim Nunes (1)

(You don’t have enough reputation to patrol this edit.)

[title] Input Cable
[* 1] Insert the AC input cable through the LEFT gland.
[* 5] Connect the ground wire to the ground block.
[* 2] Screw the RED wire of the INPUT cable to the terminal lug just above the red wire from the wiring harness.
- [* 10] Ensure both Input cable Furrles have good contact directly to the contactor pads and the screw is tight. Torque Specs are on the relay label.
- [* 9] Furrles required on finely stranded cables. Preventative maintenance. It is recommended the terminals are inspected annually to ensure the screw connection is tight.
+ [* 10] Ensure both Input cable Ferrules have good contact directly to the contactor pads and the screw is tight. Torque Specs are on the relay label.
+ [* 9] Ferrules required on finely stranded cables. Preventative maintenance. It is recommended the terminals are inspected annually to ensure the screw connection is tight.
[* 7] Screw the BLACK wire of the INPUT cable to the terminal lug just above the black wire from the wiring harness.
[* 10] Tip - run the small power wire to the controller in low in the enclosure.


Step #6 edited: [Step edited]

Edited by Tim Nunes (1)

(You don’t have enough reputation to patrol this edit.)

[title] Connect EV Cable
[* 2] Secure the wire ferrules RED and BLACK wires on the EV cable directly to contactor.
- [* 10] Ensure both EV cable Furrles have good contact directly to the contactor and the screw is tight. Torque Specs are printed on relay label.
- [* 9] Furrles required on EV cable. Preventative maintenance. It is recommended the terminals are inspected annually to ensure the screw connection is tight.
+ [* 10] Ensure both EV cable Ferrules have good contact directly to the contactor and the screw is tight. Torque Specs are printed on relay label.
+ [* 9] Ferrules required on EV cable. Preventative maintenance. It is recommended the terminals are inspected annually to ensure the screw connection is tight.
[* 10] Tip - run the low voltage wires on the bottom. Ensure there is plenty of clearance.


Step #10 edited: [Step edited]

Edited by carl oppedahl (2)

(You don’t have enough reputation to patrol this edit.)

[title] Display and Temperature Sensor
[* 9] Static sensitive - Lift display by board edges. Do not touch components.
[* 1] Remove protective film from display
[* 2] Attach display to lid using 4 coarse threaded screws.
-[* 3] Connect 6 pin cable to display on left side. (connector under the BOOT and RESET buttons.
+[* 3] Connect 6 pin cable to display on left side. (connector under the BOOT and RESET buttons.)
[* 5] Peel the backing on the tape and mount the sensor then connect the temperature sensor to the 4 pin connector on the OpenEVSE controller.