Introduction

  • Warning Assembly of a Electric Vehicle charging station requires wiring Alternating Current (AC) components that will be exposed to voltages from 100 to 250v. If you do not have the experience and knowledge required to safely work with AC voltages please consult with an experienced electrician for assistance and inspection of your work.
  • Note Regularly inspect your charging station. Pay special attention to excess heat, components, handles, and wiring will be warm but they should not be HOT...
  • Always Disconnect your charging station from power before performing an inspection and/or maintenance
Place (4) foam washers on (4) - 10mm M2.5 screws. Flip lid upside down and stack as follows:    Foam seal, then LCD clear window (remove protective coating from both sides) and finally the LCD window brace (remove protective coating). Place the (4) - 10mm M2.5 screws through the lid with the foam washer on the outside. Compress foam and thread the (4) - Hex Standoffs. Tighten each one hand tight, compressing the foam.
  • Place (4) foam washers on (4) - 10mm M2.5 screws.

  • Flip lid upside down and stack as follows: Foam seal, then LCD clear window (remove protective coating from both sides) and finally the LCD window brace (remove protective coating).

  • Place the (4) - 10mm M2.5 screws through the lid with the foam washer on the outside. Compress foam and thread the (4) - Hex Standoffs. Tighten each one hand tight, compressing the foam.

Add Comment

Mount the water resistant button switch to the enclosure lid, rubber seal on the outside. Do not over-tighten seal. If it squeezes out of place, the button is too tight. Test enclosure lid for water tightness.  Spray water around the LCD window and button, ensuring that water does not leak to the back side of the lid. Adjust as necessary. Using (4) - 6mm M2.5 screws, mount LCD module to the lid.
  • Mount the water resistant button switch to the enclosure lid, rubber seal on the outside. Do not over-tighten seal. If it squeezes out of place, the button is too tight.

  • Test enclosure lid for water tightness. Spray water around the LCD window and button, ensuring that water does not leak to the back side of the lid. Adjust as necessary.

  • Using (4) - 6mm M2.5 screws, mount LCD module to the lid.

  • Screws should be secure. Take care not to over-tighten.

  • Connect the 3-pin cable connector to the LCD module. Strip wires about 1/2", fold in half stripped wire and screw into the switch screw lugs.

  • Connect the 4-pin connector to the LCD. Note the color that represents the ground wire (green in picture).

  • Optional - Insert a CR1220 or CR1225 coin cell into the battery holder. If using charging station timers this will keep time during power outages.

Add Comment

Mount OpenEVSE  board to the mounting plate with hex stand-offs and  (8) - M2.5 x 6mm  screws.
  • Mount OpenEVSE board to the mounting plate with hex stand-offs and (8) - M2.5 x 6mm screws.

  • Mount ground bar from the top to the mounting plate using (2) - 5/8" self-tapping screws.

  • Mount the Packard C240C contactor from the top to the plate with (4) - 1/4" self-tapping screws.

  • Do not over-tighten the self-tapping screws. Tighten only until fully threaded and secure.

Add Comment

Review the connection diagram for the board you received in your kit. This guide depicts the latest board OpenEVSE v4.
  • Review the connection diagram for the board you received in your kit. This guide depicts the latest board OpenEVSE v4.

    • v4 After July 2015

  • V4 Download image

  • Connections are slightly different between board versions. Refer to these diagrams if the image in this guide does not match your board version.

Add Comment

Connect OpenEVSE AC line to the incoming AC side of the contactor. Connect OpenEVSE Ground to Ground Block. Packard - Connect contactor coil to the OpenEVSE AC relay output (v4 middle). Kits shipping after July 2015 include a MOV V275LA20AP (red disk Metal Oxide Varistor) to reduce chatter noise created by the bouncing contactor coil.
  • Connect OpenEVSE AC line to the incoming AC side of the contactor. Connect OpenEVSE Ground to Ground Block.

  • Packard - Connect contactor coil to the OpenEVSE AC relay output (v4 middle).

  • Kits shipping after July 2015 include a MOV V275LA20AP (red disk Metal Oxide Varistor) to reduce chatter noise created by the bouncing contactor coil.

    • If present, connect the red MOV across the AC_Relay terminals on the OpenEVSE board. This shares terminal positions with the AC Relay coil wires.

  • Connect OpenEVSE AC Test (v4 top block or V3 middle) to the hot line of the contactor output (J1772 side). V3 Hot only, V4 both Hot and Hot/Neutral.

  • Connect the Ground wire from the ground block to the OpenEVSE board.

Add Comment

Install Cable glands on the enclosure. If using a large gland for the input cable, use a step drill to enlarge the hole. (Left as built in this guide)
  • Install Cable glands on the enclosure. If using a large gland for the input cable, use a step drill to enlarge the hole. (Left as built in this guide)

  • Mount plate to Enclosure box using q6 - self tapping screws (2 top, 2 middle 2 bottom).

Add Comment

Thread BOTH AC lines  through the Ground Fault Coil (4-pin). If you are using the OpenEVSE 40A J1772 Cable, this is both the red pairs AND the black pairs. Thread one AC line (either side Hot1 or side Hot2) through the current-measurement CT (2-pin OpenEVSE Current CT) .       If you are using the OpenEVSE 40A J1772 Cable, this is either the red pair OR the black pair of wires.
  • Thread BOTH AC lines through the Ground Fault Coil (4-pin). If you are using the OpenEVSE 40A J1772 Cable, this is both the red pairs AND the black pairs.

  • Thread one AC line (either side Hot1 or side Hot2) through the current-measurement CT (2-pin OpenEVSE Current CT) . If you are using the OpenEVSE 40A J1772 Cable, this is either the red pair OR the black pair of wires.

Add Comment

Connect the 4-pin GFCI CT connector to the OpenEVSE board. This coil has two black wires and two orange self-test wires looped through the coil with a 4 pin connector. Orange Self test wires positioned to the inside Black GFCI CT wires to the outside.
  • Connect the 4-pin GFCI CT connector to the OpenEVSE board. This coil has two black wires and two orange self-test wires looped through the coil with a 4 pin connector. Orange Self test wires positioned to the inside Black GFCI CT wires to the outside.

  • Deluxe kits - Connect the current measurement CT to the 2 pin connector (either direction is fine).

  • Connect the J1772 pilot line (see below for common colors) to the OpenEVSE pilot screw terminal connection.

    • OpenEVSE Quick Charge Power and Tesla PURPLE, Leviton ORANGE, Yazaki BLUE

Add Comment

If using the OpenEVSE Ultra Flexible Cable, the ends are factory terminated with sleeve ferrules.
  • If using the OpenEVSE Ultra Flexible Cable, the ends are factory terminated with sleeve ferrules.

  • Other J1772 cables especially those with fine stranding Data Bulletin should be terminated with appropriately sized and crimped sleeve ferrules. If your cable has thinner power conductors, then fold each stripped conductor in half to double up and increase the contact area in Lug.

  • Insert terminated conductors into the lugs and securely tighten screws.

  • Tighten the J1772 cable gland and check its integrity.

Add Comment

Insert the AC Input cable through a Cable Gland and assemble loosely into the hole in the box. Strip the insulation off about 3/4". For smaller conductors  strip extra and fold Conductor in half (if possible) to fill the lug and increase the conducting contact area. Check the color code for your country and plug type as it varies region by region. Pictures show US 3 wire (Green, White, Black). Note US 4 wire (Green, White, Black, Red)  White Neutral not used and should be capped.
  • Insert the AC Input cable through a Cable Gland and assemble loosely into the hole in the box.

  • Strip the insulation off about 3/4". For smaller conductors strip extra and fold Conductor in half (if possible) to fill the lug and increase the conducting contact area.

  • Check the color code for your country and plug type as it varies region by region. Pictures show US 3 wire (Green, White, Black). Note US 4 wire (Green, White, Black, Red) White Neutral not used and should be capped.

  • Insert wires into lugs and tighten. The 50A kit supports both Split Phase US (Hot, Hot and Ground) and single Phase (Hot, Neutral, Ground) at a voltage of 208 - 240v AC.

  • Tighten the cable gland and check its integrity. Check the input wires are secure.

Add Comment

Connect the ground (Green) from the AC cord to the ground block. Connect the Ground from the J1772 cable to the ground block.
  • Connect the ground (Green) from the AC cord to the ground block.

  • Connect the Ground from the J1772 cable to the ground block.

  • Connect the 4 pin LCD cable. Ensure GND marked on LCD matches Ground on OpenEVSE board (pin closest to board edge).

Add Comment

Power ON with programmer or USB serial if possible.  If necessary power with AC using extreme caution.
  • Power ON with programmer or USB serial if possible. If necessary power with AC using extreme caution.

  • If display text is dim or not present adjust LED contrast (VR-1) located on the right side of the Display Module.

  • When adjusting, be gentle. Do not force past the stop in either direction. If forced past the stop, the part will no longer function.

  • Secure the enclosure lid. Tighten the screws slowly alternating across and top, middle and bottom.

Add Comment

To Enter the Menu Press and hold the button (long press). Press and release (short press) to scroll through Options.
  • To Enter the Menu Press and hold the button (long press). Press and release (short press) to scroll through Options.

  • Set "Service Level" to Level 2. Menu=> Setup => Service Level.

  • Set Current to desired Value (80% of your circuit breaker value). Menu => Setup => Max Current.

  • Enable GFCI Self Test. Menu => Setup => GFI Self Test

Add Comment

Finish Line

16 other people completed this guide.

Attached Documents

Christopher Howell

Member since: 07/05/2014

4,550 Reputation

14 Guides authored

0 Comments

Add Comment

View Statistics:

Past 24 Hours: 33

Past 7 Days: 197

Past 30 Days: 773

All Time: 23,191